Milestone 16.7 (November 13, 2023 - December 8, 2023)

Milestone Goals:

Week of November 20, 2023 (Milestone 16.7)

Team Capacity:

  • 1 BE

Goals:

Week of November 27, 2023 (Milestone 16.7)

Team Capacity:

  • 1 BE

Goals:

  • https://gitlab.com/gitlab-org/gitlab/-/issues/428402 Finalize the proposed solution. We would have a clear understanding of what changes are needed on Rails, what information would be sent by Rails to Runner in the job payload, how Runner would use this job payload to authenticate to GCP and access the secrets.

Week of December 4, 2023 (Milestone 16.7)

Team Capacity:

  • 1 BE

Goals:

Week of December 11, 2023 (Milestone 16.7)

Team Capacity:

  • 1 BE

Goals:

Milestone 16.8 (December 18, 2023 - January 12, 2024)

Milestone Goals: