Enterprise Applications - PMO

About Us

We are a global team dedicated to developing and managing cutting edge IT systems and business processes.

The Enterprise Applications PMO oversees portfolio and program management within the EntApps organization. We collaborate with business teams during planning activities to align with top priorities. Our services include portfolio, program and resource management, along with project tracking and reporting.

Our Team

Explore our team’s structure in the organization chart.

Our Services

IT EntApps Portfolio Planning & Prioritization: A 5-Step Framework

it-pmo

The IT EntApps Portfolio planning & prioritization process has 5 steps:

  1. Portfolio of Projects
  2. Prioritization
  3. T-Shirt Sizing
  4. Resources & Capacity Planning
  5. Project Commits

Portfolio of Projects

This section provides an inventory of all the committed and planned projects for IT Enterprise Applications. Internal team members can use the IT EntApps Portfolio tracker to track in-flight initiatives. EntApps portfolio priorities must align with the company objectives.

Project Prioritization

The IT EntApps Project Prioritization tracker serves as a centralized tool to log and manage new projects and initiatives. The PMO team evaluates these entries during the EntApps Monthly Business Review sessions.

T-Shirt Sizing

Involves identifying the project’s:

  • Estimated Level Of Effort (LOE)
  • Duration
  • Roles & Responsibilities

Resources & Capacity Planning

Achieved by:

  • Identifying all resource within the team
  • Estimating the capacity requirements for activities such as “Keeping the Lights On” (KTLO), administrative tasks, management, and project work.

Project Commits

All projects added to the IT EntApps Portfolio tracker are assigned resources based on priority and categorized under the following labels:

  • Committed: Projects that are in-flight / being worked on.
  • Planned: Projects that will be picked up once the resources from a committed project becomes available.

Release Management

The release management plan helps the IT EntApps team to:

  • Establish a standardized process.
  • Implement the release management strategy.
  • Maintain consistency and predictability in releases.
  • Communicate changes regularly and transparently.

Release Calendar

it-pmo

How We Work

Governance and Program Management Methodology

Visit the Governance and IT Program Management page to understand the methodology adopted by the IT EntApps PMO team for all GitLab EntApps programs aimed at achieving the following objectives:

  • Ensure robust results and efficient execution.
  • Scope projects effectively, aligning with iterative values.
  • Engage relevant stakeholders to foster collaboration.
  • Maintain transparent and compliant documentation practices.

Project Epics & Issues

When assigned to a project, the IT EntApps PMO team is responsible for creating and maintaining the project Epic. A single parent Epic is created together with (up to) 5 child Epics, each representing a distinct phase of the System Development Lifecycle (SDLC). Issues are used as a means to collaborate on ideas, troubleshoot problems, and strategize for their tasks. By using issues, teams can share and discuss proposals internally or involve external collaborators in the process.

To maintain uniformity across all PMO-led projects, the team follows the same Epic templates.

System Development Lifecycle (SDLC)

The System Development Lifecycle outlines a structured set of activities conducted at each project stage.

it-pmo

Intake

The Intake process begins with the completion of a business requirements document (BRD). This phase bridges the gap between business stakeholders defining project goals and the development team responsible for implementation.

Define

The Define phase focuses on articulating the business problem and establishing the definition of done. It includes identifying use cases, affected technologies, and requirements. The primary goal is to document processes and impacted areas rather than resolve every detail. Before moving to the Design phase, approval is obtained from key stakeholders to ensure accuracy and completeness of business requirements.

Design

The Design phase establishes a roadmap for the future state of the project. The project team collaborates with stakeholders to refine requirements and design processes that align with business goals. This phase addresses outstanding details and resolves any questions from earlier stages.

Build

During the Build phase, the project team collaborates with stakeholders to develop scalable solutions that meet business requirements while adhering to best practices.

Test

In the Test phase, the project team works with stakeholders to create test scripts and oversee the User Acceptance Testing (UAT) process, ensuring solutions meet the defined requirements.

Deploy

The Deploy phase involves creating a comprehensive deployment plan in collaboration with implementation teams. Activities include finalizing launch plans, enabling users, and managing go-live communications to ensure a smooth transition.

Hypercare

Hypercare is the phase immediately following the deployment or launch of a new process in production. During this period, enhanced support is provided to ensure a seamless transition and successful adoption of the new system.

Maintenance

The Maintenance phase begins after the new process becomes fully operational. It ensures the process continues to function as designed, with repairs or upgrades performed as necessary.

Issue Boards

IT EntApps teams use GitLab issue boards to strategically plan, organize, and visualize their work. To learn more about how IT EntApps teams manage issue boards, refer to each team’s respective page.

Labels

The IT EntApps teams use labels to efficiently categorize issues and epics. A well-maintained, concise label list facilitates dynamic filtering and streamlined management of work. All labels are created within the gitlab.com/gitlab-com top-level group, making them applicable across all projects.

To better organize and manage their work, the IT teams have different label categories. Click on each category to view the current labels utilized by the IT teams:

IT EntApps Planning Process

There are several activities that take place to prepare for new commits and report on the current ones:

  • Project List & Priorities from Business: The IT EntApps PMO team reaches out to Business stakeholders to get a list of projects and priorities for upcoming work.
  • IT EntApps PMO & Leadership - Upcoming Priorities Review: The PMO team reviews the business projects and priorities with IT EntApps Leadership to add initiatives to the upcoming commits tracker.
  • Cross Functional Meeting - Commits Review: The IT EntApps PMO team hosts the IT EntApps Portfolio Planning mmeetings to review the list of projects and priorities with Business stakeholders.
  • Commits - Corporate Rank: The IT EntApps Leadership works with the business leaders to rank the initiatives in order of priority for the company.
  • Upcoming Commits Shared with the Business: IT EntApps PMO team shares the upcoming commits with the Business stakeholders.

FY25 Q4 Calendar

it-pmo

FY26 Q1 Calendar

it-pmo1

FY26 Q2 Calendar

it-pmo2

FY26 Q3 Calendar

it-pmo3

FY26 Q4 Calendar

it-pmo4

Meetings

Meetings Protocol

The team follows GitLab meeting practices and standards.

  • Every meeting has an agenda.
  • All agendas are stored in the PMO Team Meetings shared drive.
  • The IT PMO team lead all meetings related to projects.

IT EntApps Governance

IT EntApps Leadership Meeting

  • Purpose: Every week the IT Leadership team has a dedicated time to sync up and discuss current activities (urgent and important) that impacts the whole team.
    • Frequency: Weekly, on Mondays
      • The time of this meeting may vary to accommodate the different timezones of the IT / Business Technology team members.
    • Participants: VP, IT (host), PMO, Enterprise Applications Leadership.

IT EntApps All Hands

  • Purpose: Share company updates, stay connected, and receive feedback.
    • Frequency: Quarterly (on the first week of the new quarter)
    • Participants: VP, IT (host), all IT cross functional teams.

Stakeholder Management Meetings

Project Status Meetings

  • Purpose: For each project led by the IT PMO team, a Project Status Meeting is organized to review the project’s current state, address ongoing tasks, and discuss any blockers.
    • Frequency: Weekly or every 2 weeks
    • Participants: IT EntApps PMO (host), Business DRI(s), Project Subject Matter Experts (SMEs)

IT EntApps Portfolio Review Meetings (Lead to Cash, CRO and G&A)

  • Purpose: During these meetings the IT PMO team discuss roadmap & timelines, shifts in priorities and alignment to goals.
    • Frequency: Monthly (on the third week of each month)
    • Participants: IT EntApps PMO (host), Business DRI(s).

IT EntApps Portfolio Planning (Lead to Cash, CRO and G&A)

  • Purpose: Discuss roadmap & timelines, shifts in priorities, alignment to goals. This is a strategic meeting to ensure that teams are aligned with their key business partners and have clarity on our shared roadmap.
    • Frequency: Quarterly (on the third week of the month before quarter end)
    • Participants: IT EntApps PMO (host), Business & IT EntApps Leadership.

How To Connect With Us

IT EntApps PMO Slack Channels

  • #entapps-portfolio-planning is the primary channel for all EntApps Portfolio related conversations. This is where GitLab team members can link to their issues, ask for help, direction, and get general feedback from members of the PMO team.

Governance and IT Program Management
Describes the program methodology for GitLab IT programs to ensure strong results and execution in an efficient way, proper scoping consistent with our value of iteration, correct stakeholders consistent with our value of collaboration and proper documentation for compliance consistent with our transparency value.