External CI Keyword

Project plan to add the ’external’ keyword to our CI

Weekly Project Plan

Epic: https://gitlab.com/groups/gitlab-org/-/epics/10866

Milestone 16.5 (September 17, 2023 - October 13, 2023)

Goals:

Week of Oct 09-13

Milestone 16.6 (October 17, 2023 - November 10, 2023)

Goals:

Week of Oct 16-20

Week of Oct 23-27

Week of Oct 30 Nov 03

Week of Nov 06-10

  • Due to other concurring priorities we do not expect further work beside documenting the current state of art for the moment.

Milestone 16.7 (November 13, 2023 - December 8, 2023)

Goals:

  • We do not forsee any ability for the team to work on this effort in this milestone due to concurrent priorities

Milestone 16.8 (December 11, 2023 - January 12, 2024)

Goals:

  • We do not forsee any ability for the team to work on this effort in this milestone due to concurrent priorities

Milestone 16.9 (January 15, 2024 - February 9, 2024)

Goals:

  • We do not forsee any ability for the team to work on this effort in this milestone due to concurrent priorities
Last modified December 13, 2023: Move development files in place (c26f66f9)