CI Primary Key Conversions - Weekly Project Plan

Weekly Project Plan for converting the primary keys to bigint - Pipeline Execution Group.

CI Data Partitioning - Weekly Project Plan

Milestones Goals

  • 16.9: backfill of ci_builds fk completed
  • 17.0: primary key conversion to bigint for ci_pipelines completed
Archive

Week of August 7, 2023

Team Capacity:

  • 1 BE

Goals:

Bigint conversion
  • Verify foreign key backfill progress for ci_pipelines.auto_canceled_by_id
  • Merge MR to init conversion for ci_sources_pipelines.pipeline_id and ci_sources_pipelines.source_pipeline_id
  • [~] Sync create index for ci_pipeline_messages.pipeline_id (moved to 16.4 and it’s under ~“workflow::in review”)

Week of August 14, 2023

Team Capacity:

  • 1 BE

Goals:

Bigint conversion
  • Verify foreign key backfill progress for ci_pipelines.auto_canceled_by_id, ci_sources_pipelines.pipeline_id and ci_sources_pipelines.source_pipeline_id
  • [~] Create foreign key constraint for ci_pipeline_messages.pipeline_id and swap the columns (moved to 16.4)

Week of August 21, 2023

Team Capacity:

  • 1 BE

Goals:

Bigint conversion
  • Verify foreign key backfill progress for ci_pipelines.auto_canceled_by_id, ci_sources_pipelines.pipeline_id and ci_sources_pipelines.source_pipeline_id
  • [~] Async create index for ci_pipeline_chat_data.pipeline_id and ci_stages.pipeline_id (under ~“workflow::in review”)

Week of August 28, 2023

Team Capacity:

  • 1 BE

Goals:

Bigint conversion
  • Verify foreign key backfill progress for ci_pipelines.auto_canceled_by_id
  • Async create index for ci_sources_pipelines.pipeline_id and ci_sources_pipelines.source_pipeline_id (max 2 index creation per week)

Week of September 4, 2023

Team Capacity:

  • 1 BE

Goals:

Bigint conversion
  • [~] Async create index for ci_pipelines.auto_canceled_by_id (MR deployed, need to verify)
  • Sync create index for ci_pipeline_chat_data.pipeline_id
  • Foreign key for ci_pipeline_chat_data.pipeline_id
  • Sync create index for ci_pipeline_messages.pipeline_id
  • Create foreign key constraint for ci_pipeline_messages.pipeline_id and swap the columns
  • Async create index for ci_pipeline_chat_data.pipeline_id and ci_stages.pipeline_id
  • [~] Sync create index for ci_stages.pipeline_id (need to wait for the async index creation)
  • [~] Create foreign key constraint for ci_stages.pipeline_id
  • When postgres has upgraded to 14, init conversion for: (PG for main is still at 12.9, need to wait for the upgrade)
    • [~] p_ci_builds.auto_canceled_by_id
    • [~] p_ci_builds.upstream_pipeline_id
    • [~] p_ci_builds.commit_id

Week of September 11, 2023

Team Capacity:

  • 1 BE

Goals:

Bigint conversion
  • [~] Sync create index and foreign key constraint, and swap for ci_pipelines.auto_canceled_by_id (index)
  • [~] Sync create index and foreign key constraint, and swap for ci_sources_pipelines.pipeline_id and ci_sources_pipelines.source_pipeline_id
  • Async create index for ci_pipelines.auto_canceled_by_id (MR deployed, need to verify)
  • Sync create index for ci_stages.pipeline_id (need to wait for the async index creation)
  • When postgres has upgraded to 14 (this happened on Sep 12), init conversion for:
    • [~] p_ci_builds.auto_canceled_by_id
    • [~] p_ci_builds.upstream_pipeline_id
    • [~] p_ci_builds.commit_id

Milestone 16.5 (September 18, 2023 - October 16, 2023)

Week of September 18, 2023

Team Capacity:

  • 1 BE

Goals:

Bigint conversion

Week of September 25, 2023

Team Capacity:

  • 1 BE

Goals:

Bigint conversion
  • Run analyze on partitioned tables
  • Helper and documentation for swapping columns

Week of October 2, 2023

Team Capacity:

  • 1 BE

Goals:

Bigint conversion

Week of October 9, 2023

Team Capacity:

  • 1 BE

Goals:

Bigint conversion

Week of October 16, 2023

Team Capacity:

  • 1 BE

Goals:

Bigint conversion
  • For ci_pipelines.auto_canceled_by_id
    • Sync create index (done in week 9.18)
    • Async create foreign key constraint (done in week 9.25)
    • Sync validate foreign key constraint
    • [~] Swap columns
  • For ci_sources_pipelines.pipeline_id and ci_sources_pipelines.source_pipeline_id
    • Sync create index (done in week 9.25)
    • Async create foreign key constraint (done in week 9.25)
    • Sync validate foreign key constraint
    • Swap columns
  • For ci_pipeline_chat_data.pipeline_id
    • Swap columns
  • For ci_pipeline_variables.pipeline_id
    • [~] Swap columns
  • For ci_stages.pipeline_id
    • Async create foreign key constraint (done in week 9.25)
    • Sync validate foreign key constraint
    • [~] Swap columns
  • For ci_pipeline_messages.pipeline_id
    • Sync validate foreign key constraint (done in week 9.18)
    • Swap columns
  • Init conversion for:
    • [~] p_ci_builds.auto_canceled_by_id
    • [~] p_ci_builds.upstream_pipeline_id
    • [~] p_ci_builds.commit_id

Milestone 16.6 (October 17, 2023 - November 10, 2023)

Team Capacity:

  • 1 BE

Goals:

Bigint conversion
  • For ci_pipelines.auto_canceled_by_id
    • Swap columns
  • For ci_pipeline_variables.pipeline_id
    • Swap columns
  • For ci_stages.pipeline_id
    • Swap columns
  • Init conversion for:
    • p_ci_builds.auto_canceled_by_id
    • p_ci_builds.upstream_pipeline_id
    • p_ci_builds.commit_id
  • Stretch: Remove the triggers and integer columns for:
    • ci_sources_pipelines.pipeline_id
    • ci_sources_pipelines.source_pipeline_id
    • ci_pipeline_chat_data.pipeline_id
    • ci_pipeline_messages.pipeline_id
    • [~] ci_stages.pipeline_id
    • ci_pipeline_variables.pipeline_id
    • [~] ci_pipelines.auto_canceled_by_id

Milestone 16.7 (November 13, 2023 - December 8, 2023)

Team Capacity:

  • 1 BE

Goals:

We’ll monitor progress of the foreign key backfill on ci_builds this milestone. We will continue to create the necessary MRs for updating the indexes

Bigint conversion
  • Remove the triggers and integer columns for:
    • ci_stages.pipeline_id
    • ci_pipelines.auto_canceled_by_id
  • Remove the ignore rules for:
    • ci_pipeline_chat_data.pipeline_id
    • ci_pipeline_messages.pipeline_id
    • ci_sources_pipelines.pipeline_id
    • ci_sources_pipelines.source_pipeline_id

Milestone 16.8 (December 11, 2023 - January 12, 2024)

Team Capacity:

  • 1 BE

Goals:

We are continuing to monitor the progress of the foreign key backfill on ci_builds this milestone. Improvements to backfill progress were made for a significant impact following the partitioning of ci_builds last milestone. It now looks like the backfill should complete within 6 weeks rather than 6 months. As such we are pulling the planned work up.
After discussion with the database team, it seems like we are good to go ahead and swap the primary key column on ci_pipelines before the backfill on ci_builds completes. As such we intend to complete that in 16.8. This will allow us to move forward with partitioning of ci_pipelines while the backfile contines.

Bigint conversion
  • Remove the ignore rules for:
    • ci_stages.pipeline_id
    • ci_pipelines.auto_canceled_by_id
    • ci_pipeline_variables.pipeline_id
  • Swap columns for ci_pipelines.id

Milestone 16.9 (January 15, 2024 - February 9, 2024)

Team Capacity:

  • 1 BE

Goals:

Backfill of bigint Pipeline FKs is projected to finish near the end of January 2024. As such we should be able to create the indexes and foreign key constraints for p_ci_builds.

Bigint conversion
  • Create indexes and/or foreign key constraint and swap columns for:
    • p_ci_builds.auto_canceled_by_id
    • p_ci_builds.upstream_pipeline_id
    • p_ci_builds.commit_id

Milestone 16.10 (February 12, 2024 - March 8, 2024)

Team Capacity:

  • 1 BE

Goals:

Backfill of bigint Pipeline FKs is projected to finish near the end of January 2024. We should be able to remove the triggers and the integer column on ci_pipelines once the backfill is complete and the foreign key has been updated on p_ci_builds.

Bigint conversion
  • Remove the ignore rules for ci_pipelines.id
  • Remove the triggers and integer columns for ci_pipelines.id

Milestone 16.11 (March 11, 2024 - April 12, 2024)

Team Capacity:

  • 1 BE

Goals:

We will plan to have the MRs for next milestone ready to go in this milestone as well given Tian’s limited availability in 17.0.

Bigint conversion
  • Remove the triggers and integer columns for:
    • p_ci_builds.auto_canceled_by_id
    • p_ci_builds.upstream_pipeline_id
    • p_ci_builds.commit_id

Milestone 17.0 (April 15, 2024 - May 10, 2024)

Team Capacity:

  • 0 BE (Note: Tian will be frontline responder this milestone)

Goals:

Merging of the final MRs to remove the ignore rules. This should wrap up the conversion of the ci_pipelines PK. There are other tables requiring PK conversion, but they are smaller and less connected. Their completion will be planned into other team work.

Bigint conversion
  • Remove the ignore rules for:
    • p_ci_builds.auto_canceled_by_id
    • p_ci_builds.upstream_pipeline_id
    • p_ci_builds.commit_id