CI Steps - Key Project Plan
Weekly Engineering Project plan for CI Steps
Weekly Project Plan
Epic: https://gitlab.com/groups/gitlab-org/-/epics/11535
%16.5
Week of 2023-09-17
- Engineering strategy meeting to discuss an initial iteration plan
Week of 2023-09-25
- Clarify the iteration plan and next steps, with estimates of:
- Architectural Design doc updates to be merged in next 2-3 weeks
- MVC to be completed in the next 2-3 months
Week of 2023-10-02
- Iterating on technical strategy in Architectural blueprint
Week of 2023-10-09
- Iterating on technical strategy in Architectural blueprint
- Designate a Pipeline Authoring (Rails) DRI to start collaborating with the Runner DRI
%16.6
Week of 2023-10-16
- Set up sync meeting between Engineering and Product to discuss current progress and align on technical & product strategy and goals
- Iterate on the Architectural blueprint MR
Week of 2023-10-23
- Iterate on the Architectural blueprint MR
- Update the Step-Runner code based on decisions made in the blueprint
Week of 2023-10-30
- Resolved threads and merge the Architectural blueprint MR
- Update the Step-Runner code to align with the blueprint
- Implement the golang, bash and docker engines
Week of 2023-11-06
- Update the Step-Runner code to align with the blueprint
- Have it work with local Steps
- Implement the golang, bash and docker engines
%16.7
Week of 2023-11-13
- Implement the golang, bash and docker engines
- Start determining which teams internally who could dogfood the feature
Week of 2023-11-20
- Implement the golang, bash and docker engines
Week of 2023-11-27
- Build the Lua engine as a POC (adding in ability to script in unsupported languages)
Week of 2023-12-04
- Build the Lua engine as a POC (adding in ability to script in unsupported languages)
- Record a demo with working MVC that aligns with the blueprint
%16.8
Largely TBD given that this is a forecast 2 months out and subject to other team member availability
Week of 2023-12-11
- Build out a few more officially supported steps, such as fetch sources, caching, artifacts. (scope TBD)
Week of 2023-12-18
- Create a runner feature flag to skip built-in steps.
- Discuss feasibility of getting Runner capacity to contribute (even starting in %16.7 or %16.8 once work can be parallelized)
Week of 2023-12-25
- End of Year PTO 🎄
Week of 2024-01-02
Discussg parallel tracks of effort (WIP plans and DRIs):
- Implement GitLab CI Steps support in Rails. This will elevate the “steps in env variable” to a properly supported syntax, including CI Editor support. This also involves collaboration with a Rails Engineer on Pipeline Authoring.
- Add more test coverage (unit tests, integration tests, e2e tests (and for each engine)). Up until this point, test coverage is expected to be minimal.
- Build support for GitHub Actions in CI Steps (up until this point, only GitLab-based steps will be supported)
- Setup publishing workflows for Step Runner and all the officially supported engines and steps. Because users will be referencing our steps directly in their workflows, we need to publish them.
- Write clear documentation on how users should import steps. E.g. which ones need docker, what the recommended use is, etc… I don’t think the Component Catalog will be ready to curate these yet, but we can at least have some nice README’s when browsing our steps sub-group.
Last modified June 27, 2024: Fix various vale errors (