GCP Secrets Integration - Weekly Project Plan

GCP Secrets Integration - Weekly Project Plan - Pipeline Security Group

This project has been released.

Archive

Click to view past plans

Milestone 16.7 (November 13, 2023 - December 8, 2023)

Milestone Goals

Week of November 20, 2023 (Milestone 16.7)

Team Capacity

  • 1 BE

Goals

Week of November 27, 2023 (Milestone 16.7)

Team Capacity

  • 1 BE

Goals

  • https://gitlab.com/gitlab-org/gitlab/-/issues/428402 Finalize the proposed solution. We would have a clear understanding of what changes are needed on Rails, what information would be sent by Rails to Runner in the job payload, how Runner would use this job payload to authenticate to GCP and access the secrets.

Week of December 4, 2023 (Milestone 16.7)

Team Capacity

  • 1 BE

Goals

Week of December 11, 2023 (Milestone 16.7)

Team Capacity

  • 1 BE

Goals

Milestone 16.8 (December 18, 2023 - January 12, 2024)

Milestone Goals

Last modified May 18, 2024: Remove engineering exclusion and fix related errors (bed28b7f)