Boards on Saved Views: Project Example
Timeline
gantt
title Lifecycle Boards
dateFormat YYYY-MM-DD
axisFormat %b %d
section Milestones
18.10 :m1810, 2026-02-14, 2026-03-13
18.11 :m1811, 2026-03-14, 2026-04-10
19.0 :m190, 2026-04-11, 2026-05-15
19.1 :m191, 2026-05-16, 2026-06-12
19.2 :m192, 2026-06-13, 2026-07-10
19.3 :m193, 2026-07-11, 2026-08-14
section Pre-work
Requirements discovery :discovery, 2026-02-14, 2026-04-18
Groundwork :prereqs, 2026-03-14, 2026-04-24
section Active development
Alpha :alpha, 2026-04-18, 2026-05-29
Internal rollout :crit, milestone, 2026-05-29, 0d
GA :ga, 2026-05-29, 2026-07-10
GitLab.com rollout :crit, rollout, 2026-06-26, 2026-07-10
section Feedback and clean-up
Post-GA follow-ups :followups, 2026-06-26, 2026-08-14
Stages
We break projects into time-limited stages and cut scope to a minimal viable change to:
- Reduce cognitive load — engineers work on smaller changes, smaller sets of requirements, and fewer issues.
- Simplify project management and spot delays early — smaller stages are easier to keep on track and it’s easier to notice when one is late.
- Surface bugs and feedback earlier.
| Stage | Outcome |
|---|---|
| Requirements discovery | Decision on scope for subsequent stages. Work broken down into issues. Rough estimation of the project. Clear definition of what is out of scope. |
| Groundwork | Refactorings and adaptations that make the rest of the development easier. |
| Alpha | Core workflow can be used for dogfooding and internal testing, but can be rough on the edges. Includes addressing internal testing feedback. |
| GA | The smallest coherent experience we’re comfortable releasing to users. Includes addressing user feedback from alpha, fixing rough edges, and a feature flag rollout period (~2 weeks before milestone cut-off). |
| Post-GA follow-ups | Features deferred past the initial release, user feedback, code and test cleanup. Must be completed within 1–2 milestones after GA. When in doubt, put issues in out of scope. |
| Out of scope | No commitment. May be done later, reprioritized, or closed. |
Epic organization
Lifecycle Boards (top-level epic)
├── Lifecycle Boards — Requirements discovery
│ ├── UX discussions (issue)
│ ├── Lifecycle Boards — Card (epic)
│ ├── Lifecycle Boards — Columns (epic)
│ └── ...
├── Lifecycle Boards — Groundwork
│ ├── Refactor work item listing page (epic)
│ ├── Load work items via REST API instead of GraphQL on listing pages (epic)
│ └── ...
├── Lifecycle Boards — Alpha
│ ├── Status columns (epic)
│ │ ├── Load available statuses (issue)
│ │ └── Load work items by column (issue)
│ ├── Card (epic)
│ ├── API changes (epic)
│ ├── Transform view preferences dropdown into drawer (epic)
│ ├── Card drag and drop (epic)
│ │ ├── Persist changes (issue)
│ │ └── Basic animation (issue)
│ └── ...
├── Lifecycle Boards — GA
│ ├── Internal testing feedback (issue)
│ ├── Card enhancements (epic)
│ ├── Feature flag rollout (epic)
│ ├── Card drag and drop (epic)
│ │ ├── Improved animation (issue)
│ │ └── Highlight available and unavailable columns (issue)
│ └── ...
├── Lifecycle Boards — Post-GA follow-ups
│ ├── User feedback (issue)
│ ├── Feature flag removal (epic)
│ ├── Old code cleanup (epic)
│ ├── Tests cleanup (epic)
│ └── ...
└── Lifecycle Boards — Out of scope